Section 4 Starting Up; Factory And Site Acceptance Testing; Commissioning Checklist - ABB REL650 Commissioning Manual

Relion 650 series, line distance protection
Hide thumbs Also See for REL650:
Table of Contents

Advertisement

1MRK 506 383-UEN A
Section 4
4.1
4.2
Line distance protection REL650 2.2 IEC
Commissioning manual
Starting up

Factory and site acceptance testing

Testing the proper IED operation is carried out at different occasions, for example:
Acceptance testing
Commissioning testing
Maintenance testing
This manual describes the workflow and the steps to carry out the commissioning
testing.
Factory acceptance testing (FAT) is typically done to verify that the IED and its
corresponding configuration meet the requirements of the utility or industry. This
test is the most complex and in depth, as it is done to familiarize the user with a
new product or to verify a new configuration. The complexity of this testing
depends on several factors, such as:
New IED type
New configuration
Modified configuration
Site acceptance testing (SAT or commissioning testing) is typically done to verify
that the installed IED is correctly set and connected to the power system. SAT
requires that the acceptance testing has been performed and that the application
configuration is verified.
Maintenance testing is a periodic verification that the IED is healthy and has
correct settings, depending on changes in the power system. There are also other
types of maintenance testing.

Commissioning checklist

Before starting up commissioning at site, check that the following items are
available.
Single line diagram
Protection block diagram
Circuit diagram
Setting list and configuration
RJ-45 Ethernet cable (CAT 5)
Section 4
Starting up
GUID-38C2B5FA-9210-4D85-BA21-39CE98A1A84A v2
GUID-93D14E4E-5DDE-4D37-84A6-2DF0656AB73D v3